Liberty Memorial Bridge
Liberty Memorial Bridge Project Time Line
home

• June 2006 - Strip topsoil; remove trees, meat plant, and house foundation.

• June 2006 - Set up staging area and move in equipment.

• June or July 2006 – Put up screen fence and safety fence around perimeter of work area.

• July 2006 – Build dock on west side of river.

• July 2006 – Start pile driving and construction of piers 7 & 8.

• September 2006 – Start construction of the east approach bridge progressing from the abutment to the river.

• Fall 2006 – Start construction of the MSE wall at the east abutment.

• Fall 2006 – Finish piers 7 and 8 before the ice pack.

• Winter 2006 – Start pile driving and construction of piers 10 and 11.

• Winter 2006 – Start pile driving and construction of south half of the west abutment.

• Spring 2007 – Start pile driving and construction of pier 9.

• Summer 2007 – Set structural steel for river spans.

• Summer 2007 – Pour deck concrete for approach bridges.

• Spring/Summer 2008 – Pour deck concrete for river span.

• Summer 2008 – Switch traffic from old bridge to new bridge.

• Summer 2008 – Transfer utilities from old bridge to new bridge.

• Fall 2008 – Finish construction of the north half of the west approach bridge.

• Summer 2009– Finish plazas, demolition old bridge.

For Question or Comments: dot@nd.gov
North Dakota Dept of Transportation logo

This website is maintained by the ITD Dvision of the NDDOT
Copyright © 2006 North Dakota Department of Transportation. All rights reserved.

Memorial Bridge home page    News  FAQ  
 Project Time Line  Project Fact Sheet  
Project Photos   Project Development  History  Selected Design   
Bridge Design    Public involvement   Privacy Policy  

Bobby Approved

Valid CSS!

 
Level Double-A conformance icon, 
          W3C-WAI Web Content Accessibility Guidelines 1.0